Is Use of C900 for Fire Service Entry Acceptable? (2024)

Is Use of C900 for Fire Service Entry Acceptable?

2/16/2023

16 Comments

We have a building that is constructed. It has a very deep footing.

The contractor originally submitted an Ames In-Building Riser, but it's too deep for the in-building riser in the building's (essentially) existing condition.

They proposed using C900 to come under the footing, without a sleeve, going below the 12" footing and then stubbing up into the riser room without thrust blocks.

We have concernsabout restraint and a change of direction underneath the foundation.

NFPA 13 applies and C900 is a permitted material, which is what the contractor has suggested makes it acceptable.

Is routing C900 under a building footing, changing direction, and then stubbing into the building acceptable?

16 Comments

James Phifer

2/16/2023 08:17:35 am

I don't think it's a good idea, but NFPA 13, 2022 ed A6.4.3.1.1 states: The individual piping standards should be followed for load and bury depth, accounting for the load and stresses imposed by the building foundation.

Seems like a lot of weight to put on the C900 pipe.

Reply

Jesse

2/16/2023 08:18:14 am

I have concerns as well. Primarily the lack of restraint and thrust blocking at the change of direction. How are they expecting the pipe to not separate?

Reply

Anthony

2/21/2023 01:10:36 pm

This, Nothing worse than having your underground blow out during testing especially under a footer that's supporting the building.

Reply

Glenn Berger

2/16/2023 08:18:25 am

Using C900 piping below a footing w/o a sleeve may or may not be permissible. First consult the applicable authorities if this is allowed in this jurisdiction.

Since this is an existing building, I would be more accepting of this condition, than if it was for a new building. Restraints and thrust blocks would still be required.

Reply

David Kendrick

2/16/2023 08:20:05 am

!. Adequate clearance between C900 and footing.
2. If change in direction means the spigot rising through floor then change in direction is acceptable. There are industry practices as well as products approved for the purpose of restraining the joints.

If this is a product substititution you are probably justified to propose new practices to protect the piping. If it were my choice bringing a ductile pipe through the floor and floor sleeve is a good start.

We have in the past used Ductile Iron Pipe both under the footing and absolutely for the spigot through the floor.

Reply

James Evans

2/16/2023 08:21:39 am

You need to transition @ 5'-0" out from the building to Cement Lined Ductile Iron with mechanical Joint Fittings. This has been done for years and is still acceptable. I know the fashion is the new in building riser but go back to the old trusted way. It still works well.

Reply

JH

2/16/2023 08:36:32 am

James,

Could you please elaborate on the specific conditions where the jointed, cement-lined DIP riser is preferable to the Ames-type in-building riser? Thanks!

Reply

James Evans

2/16/2023 10:16:34 am

I did not say it was "Preferable", I do love the in building riser, however it does not meet every need. I will say that cement lined ductile iron is preferable over C900 going under a footing and slab.

It is never a good idea to run plastic pipe under a footing. Even in residential occupancies they prefer you use copper pipe when entering the residence.

Plastic under a footing is just calling for problems in the future.

J.James

2/16/2023 09:04:20 am

I agree with James. The riser / stub-in / lead-in should be ductile. If you choose to use C-900, it should be sleeved. I have seen a few instances where a fork truck has hit and snapped the C-900 at its base.

Reply

TC

2/16/2023 08:43:46 am

Have you considered using an In-Building Riser? All one piece stainless steel. AMES makes them from 4-inch up to 12-inch. and it will connect to the C900. You can order it in a length that will put the connection past the footing bearing zone.

Reply

James B

2/16/2023 08:48:29 am

We have had Ames make custom lengths from the factory in the past. Check into that option as well.

Reply

Ryan Hinson

2/16/2023 10:40:58 am

Every joint between pipe and fitting must be restrained against separation per NFPA 24 (2022) Section 10.6 which may include thrust blocking (10.6.1), or more likely; restrained joint systems (10.6.2), or other connection methods (10.6.3).

Of additional consideration are the limitations imposed on private fire service mains beneath buildings per NFPA 24 Section 10.4.3 regarding distance inside the building footprint, pipe joints not being under footings, and clearances between the pipe and footing.

The IBR is an ideal option for this scenario and has custom lengths for both lateral and vertical legs and already includes restraint attachments for both up- and downstream piping. See also NFPA 24 Figure A.10.4.3 which shows an acceptable riser entrance detail inclusive of no joints underneath the footing, minimum distance below the bottom of the footing, and not exceeding the allowable 10 ft distance into the building.

If using PVC or DI, the restraint requirement at the 90 el, and access to provide it, remains the same. Since this elbow is already welded on the IBR, no access is needed to it, just the room to get it installed.

Though allowed per NFPA 13 Section 6.1.4 and NFPA 24 Section 10.1.4, I would not recommend stubbing plastic pipe of any type above the floor inside the building. I have seen melted risers in riser rooms. This allowance also directly contradicts plastic pipe mfgrs' listing indicating it is only for UG FW use.

Unless this is a seismically-protected system, no sleeve through the floor slab is required per NFPA nor do you want your riser moving around inside the building. I would use the IBR and poor the floor slab patch right up to the edge of the IBR.

Reply

Mark Harris

2/16/2023 12:35:26 pm

James covered this well. Transition from PVC to ductile iron five foot outside building and several have mentioned restraint which you also have to be concerned with the Ames stainless steel riser installs.

Water material supplier will probably not have a 11 or 12 foot long flange by plain end so most likely will be a piece of ductile pipe with a MJ 90 at the base and a uniflange to transition to steel above floor.

If in a seismic area need to look at proper core or sleeve sizes for both the foundation and floor.

Reply

Casey Milhorn

2/16/2023 03:00:20 pm

I agree with changing to DI pipe at 5'-0" out. This may not be code driven, but it's definitely a good idea. Also, I'm not sure how cost compares in other parts of the country, but where I am, there is very little cost difference now between C900 and DI pipe. It used to be 50% to 70% in savings to go C900.

Reply

Chris

2/17/2023 08:54:15 am

Have them use ductile iron from the interior flange installed at a minimum height of 1'-0" AFF down under the footing and then a minimum of 5'0" from the outside face of the footing. IIRC code says piping within 5' of the building exterior shall be of a type resistant to mechanical damage, or something to that effect. And But Ames does make the IBR with different lengths of legs if you do want to stick with Ames.

Reply

James Art. FPE

2/22/2023 11:56:06 am

J.James, and R Hinson:
You both mentioned what sounded like EXPOSED* PVC (intended as underground) above the ground.
Fork lift hit the pipe? Melted pipes?

*I do not believe the PVC is listed to be used exposed like that,
which is why such pipe should be metallic!

Perhaps someone can find the code references.

Yes, there is listed CPVC, but it is small, and for very limited applications, not large commercial risers! Even that is better if protected behind or inside walls or ceilings!

Reply

    SUBMIT A QUESTION

    Why Sponsor?

    ALL-ACCESS

    GET ALL OUR TOOLS

    SUBSCRIBE

    Subscribe and learn something new each day:

    COMMUNITY

    Top ​May '24 Contributors

    Is Use of C900 for Fire Service Entry Acceptable? (3)

    Is Use of C900 for Fire Service Entry Acceptable? (4)

    Is Use of C900 for Fire Service Entry Acceptable? (5)

    Is Use of C900 for Fire Service Entry Acceptable? (6)

    Is Use of C900 for Fire Service Entry Acceptable? (7)

    Is Use of C900 for Fire Service Entry Acceptable? (8)

    Is Use of C900 for Fire Service Entry Acceptable? (9)

    Is Use of C900 for Fire Service Entry Acceptable? (10)

    Is Use of C900 for Fire Service Entry Acceptable? (11)

    Is Use of C900 for Fire Service Entry Acceptable? (12)

    SEE LEADERBOARD

    YOUR POST

    SUBMIT A QUESTION

    PE EXAM

    Get 100 Days of Free Sample Questions right to you!

    FILTERS

    All
    A1171
    ABA
    ADA
    ASCE 7
    ASME A17.1
    ASTM E1354
    Blog Thread
    Daily Discussion
    Design-documents
    EN 12845
    Explosion Protection
    Explosion-protection-prevention
    Fire Detection And Alarm Systems
    Fire Dynamics
    Flammable And Combustible Liquids
    Flammable-combustible-liquids
    FM Global
    Human-behavior
    IBC
    ICC 500
    IFC
    IMC
    IPC
    IRC
    ISO
    Means Of Egress
    NBC
    NFPA 1
    NFPA 10
    NFPA 101
    NFPA 11
    NFPA 110
    NFPA 1142
    NFPA 1221
    NFPA 13
    NFPA 13D
    NFPA 13R
    NFPA 14
    NFPA 15
    NFPA 16
    NFPA 17A
    NFPA 20
    NFPA 2001
    NFPA 214
    NFPA 22
    NFPA 220
    NFPA 24
    NFPA 241
    NFPA 25
    NFPA 291
    NFPA 30
    NFPA 307
    NFPA 30B
    NFPA 33
    NFPA 400
    NFPA 409
    NFPA 415
    NFPA 495
    NFPA 497
    NFPA 5000
    NFPA 502
    NFPA 54
    NFPA 55
    NFPA 654
    NFPA 68
    NFPA 70
    NFPA 701
    NFPA 72
    NFPA 75
    NFPA 770
    NFPA 82
    NFPA 855
    NFPA 90A
    NFPA 92
    NFPA 96
    NICET
    OBC
    Passive Building Systems
    PE Prep Guide
    PE Prep Series
    PE Sample Problems
    Poll
    Smoke Management
    Special Hazard Systems
    UFC 3-600-01
    UFC 4-021-01
    UPC
    Updates
    Water Based Fire Suppression
    Weekly Exams

    ARCHIVES

    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    November 2016
    October 2016
    July 2016
    June 2016

    PE PREP SERIES

    SEE LEADERBOARD

    RSS Feed

Is Use of C900 for Fire Service Entry Acceptable? (2024)

References

Top Articles
Latest Posts
Article information

Author: Manual Maggio

Last Updated:

Views: 6400

Rating: 4.9 / 5 (49 voted)

Reviews: 80% of readers found this page helpful

Author information

Name: Manual Maggio

Birthday: 1998-01-20

Address: 359 Kelvin Stream, Lake Eldonview, MT 33517-1242

Phone: +577037762465

Job: Product Hospitality Supervisor

Hobby: Gardening, Web surfing, Video gaming, Amateur radio, Flag Football, Reading, Table tennis

Introduction: My name is Manual Maggio, I am a thankful, tender, adventurous, delightful, fantastic, proud, graceful person who loves writing and wants to share my knowledge and understanding with you.